We have now caught up to the schedule (we were ahead before!). The block apparently wasn’t delivered until late afternoon on Tuesday, so this is all they did the first block laying day. And of course, Wednesday they didn’t work (huh?).
The original plan was to have the foundation laid by Friday and order wood and begin framing on Monday.
George has not finalized the contract with the kitchen manufacturer. Apparently it only takes 4 weeks to make the kitchen! Stay tuned….